| No delays on Patriot 
systems, defense contractor says
 WAR GAMES: After the KMT blocked the budget for 
the missiles for three years, legislators were surprised to see how much the 
price had increased when it was released
 
 By J. Michael Cole / Staff Reporter
 
 
 A US-made Patriot surface-to-air 
missile is launched during a military exercise in Yilan County on July 20, 2006.Photo: Reuters
 
 A US defense contractor yesterday denied 
local reports that efforts by Taiwan to procure two additional PAC-3 air defense 
batteries were jeopardized by political bickering and a lack of funds.
 The Chinese-language United Daily News on Monday wrote that since the US had 
agreed to sell two additional Patriot Advanced Capability-3 (PAC-3) systems in 
January last year, the military had had difficulty raising enough money to 
complete the deal, as the cost of acquisition allegedly exceeded the military¡¦s 
budget by as much as 40 percent.
 
 The report cited military sources as saying that the military had lobbied the 
Pentagon to lower the price for the two batteries on several occasions, but that 
little progress had been made, adding that the Ministry of National Defense 
would have to increase its budget for the acquisition and that delivery could be 
deferred.
 
 US authorities have warned Taipei that if it failed to make any progress by the 
end of this year, the purchase price could be -invalidated and subsequent orders 
could be higher, the report said.
 
 The two firing units are part of the US$6.4 billion arms package agreed by the 
administration of US President Barack Obama in January last year. In addition to 
fire units, one training unit and 114 PAC-3 missiles were included in the US$2.8 
billion deal.
 
 The two batteries are to complete a total of six PAC-3 defense systems sought by 
Taiwan following notification in October 2008 of four fire units and 330 PAC-3 
missiles for US$3.1 billion.
 
 KMT BOYCOTT
 
 At the heart of the alleged funding shortfall is the three-year boycott by the 
Chinese Nationalist Party (KMT) of the NT$120 billion (US$4.14 billion) budget 
for the missile defense program in the legislature from 2004 until 2007, the 
paper said. When the budget was finally released in 2007, Taiwan discovered that 
the unit cost for the PAC-3 system had gone up substantially. Legislators later 
claimed that cost overruns, estimated at US$800 million, were added to a draft 
of the letter of acceptance (LOA) for the 2008 deal, resulting in further 
delays.
 
 ¡¥ON TRACK¡¦
 
 Contacted for comment, an official at Raytheon, the US defense firm that 
manufactures the Patriot ground systems, said it was their understanding that 
the purchase of the two fire units was ¡§on track.¡¨
 
 That position was echoed by a US-based source familiar with the situation, who 
told the Taipei Times last night that the program was in the final stages and on 
schedule to be signed this fall.
 
 The ministry on Monday denied the reports and said it was proceeding with the 
purchase.
 
 Raytheon and Lockheed Martin Corp, the maker of the ¡§hit-to-kill¡¨ PAC-3 missile, 
are the two principal firms involved in the sale.
 
 Taiwan is scheduled to field the first four PAC-3 batteries by 2014. Raytheon is 
also in the process of upgrading Taiwan¡¦s three PAC-2 missile batteries, 
acquired in the 1990s, to PAC-3 configuration.
 
 The ministry was forced to deny similar rumors in May after KMT Legislator Lin 
Yu-fang (ªL§¤è) claimed that budgetary issues could force delays to three major 
procurement programs ¡X UH-60 Black Hawk helicopters, AH-64D Apache Longbow 
attack helicopters and the PAC-3 batteries.
 |