Nuclear referendum
receives go-ahead
DECISION TIME: The government wants the Fourth
Nuclear Power Plant to be completed, but the premier said it was willing to put
the issue to a referendum
By Shih Hsiu-chuan / Staff reporter
The government yesterday had a surprise change of heart, declaring an initiative
to put the controversial Fourth Nuclear Power Plant to a national referendum.
After a meeting with Chinese Nationalist Party (KMT) officials and lawmakers
yesterday, Premier Jiang Yi-huah (江宜樺) said: “The ultimate decision on this
issue of major concern to people’s lives and security, and to the nation’s
economic development in the future, shall be decided through a referendum.”
The decision was reached at a meeting presided over by President Ma Ying-jeou
(馬英九) at the Presidential Office on Sunday night and attended by Jiang, Minister
of Economic Affairs Chang Chia-juch (張家祝), party officials and several KMT
lawmakers.
Jiang said that the government maintains its position that construction of the
plant should be completed, but it will not operate commercially unless it is
safe.
However, “we would like to face public scrutiny through a referendum,” he said.
According to the plan, a referendum on halting construction of the Fourth
Nuclear Power Plant will be initiated by the KMT caucus tabling a motion next
month in the legislature, KMT caucus whip Lai Shyh-bao (賴士葆) said.
Lai said the plebiscite could be held in August as the Referendum Act (公民投票法)
stipulates that a referendum must be held no sooner than one month and no later
than six months after its proposal.
If the completion of the plant failed to win approval, there was the risk of
huge compensation payouts for breach of contract, higher electricity costs,
power shortages and even an adverse effect on economic growth, Jiang said.
Nevertheless, “we would accept the ultimate decision made by the people,” he
said.
Since 1992, when the first budget for the plant cleared the legislature, NT$264
billion (US$8.9 billion) has been poured into the project, with NT$19.7 billion
requested in this legislative session, which begins today, and a budget of NT$40
billion needed to complete its construction.
State-owned Taiwan Power Co (Taipower, 台電), the builder and operator, originally
planned to apply to the Atomic Energy Council (AEC) to load fuel rods in the
plant’s first reactor in February next year and to begin commercial operations
in October 2015.
The Fukushima Dai-ichi nuclear power plant incident of 2011 in Japan has
re-energized Taiwan’s anti-nuclear movement, with the Fourth Nuclear Power Plant
the focus of attention.
A number of flaws in the design and construction of the plant have been
identified. Adding to safety concerns over nuclear power plants in Taiwan is the
fact that they are situated in geologically unstable earthquake-prone areas.
Since the Referendum Act was enacted in 2004, there have been six national
referendums, all held on the same day as national elections — March 30, 2004, a
presidential election; January 12, 2008, a legislative election; and March 22,
2008, a presidential election.
There were two referendums on each date, but none of the proposals in the
referendums passed due to what is perceived to be the high threshold for them to
be successful.
That referendum act requires more than half of eligible voters to cast ballots
for a poll to be valid.
Elizabeth Sun (孫又文), a spokeswoman for Taiwan Semiconductor Manufacturing Co (TSMC,
台積電), the world’s largest contract chipmaker, said that while it did not take
sides on the matter, the government should ensure that industry would be able to
enjoy stable and adequate power supplies.
TSMC would not comment on whether the issue should be resolved via referendum.
Contract chipmaker United Microelectronics Corp (聯電) said that the most
important issue was ensuring sufficient power supplies.
Additional reporting by Lisa Wang
|